Installing Solar in Murray: Murray Power's Rules for Contractors
The short version: Murray has its own electric utility, Murray City Power, a municipal utility the city created in 1913. It has its own solar process, from approval and an interconnection agreement to a $250 residential net meter and a separate production meter. Since April 2025, it has also required a NABCEP Installation Certification for every solar installer in the city. If you install solar or do electrical work in Murray, your website should show you know these steps.
What is Murray City Power?
According to the city, Murray City Power is a "publicly owned, municipal electric utility." It was created in 1913 and serves about 18,000 customers, roughly 82% residential and 18% commercial and industrial. The Power Department is at 153 West 4800 South, and outages are reported to its 24-hour dispatch at 801-264-9669.
For contractors, that means Murray Power signs off on solar connections in its system, with its own paperwork and meters.
Who can install solar in Murray?
Murray's net metering page lists certification requirements that took effect in April 2025:
- Installers: a NABCEP Installation Certification. The city says it "will be mandatory for all solar installers in Murray City."
- Electricians: an S200 or S202 Electrical License.
- Sales staff: NABCEP Sales Certification.
- Engineers: NABCEP Engineering Certification or an equivalent.
What are the steps for a solar job in Murray?
The city's solar checklist lays out the process:
- Murray Power approval. Contact Murray Power at netmetering@murray.utah.gov.
- Interconnection agreement. Complete the Murray City Power Interconnection Agreement and email it in. Murray Power returns a signed copy after review.
- Building permit. Apply online, with owner, contractor and subcontractor information and the project valuation, and complete the plan submittal checklist with Murray City Building Inspection.
- Net meter purchase. A residential net meter is $250, paid to Murray City Power.
- Installation. The system needs a production meter in addition to the net meter, and a separate, manually operated safety disconnect with visible contacts between the inverter and the production meter base. Murray City Power covers the cost of the production meter.
- Final inspection with Murray City Building Inspection, at (801) 270-2431.
- Net meter installation. Murray Power's metering supervisor schedules a visit to test the system and install both meters, then the billing division activates the net meter account.
One rule is worth repeating to every customer: the city says panels may not be connected to Murray's system until the new net meter is installed. Connect early and excess production is billed as consumption.
What about net metering rates?
Murray says it "is in the process of revising its Pilot Net Metering Program," and that "the rates and policies of the existing program are subject to change." So don't promise a specific credit rate or payback on your website. Tell customers you'll walk them through Murray Power's current terms, and send them to the city's net metering page.
What should a Murray solar or electrical website say?
- A Murray page. "Solar in Murray" with the steps above in plain language. It shows customers you already know Murray Power's process.
- Your certifications, by name. NABCEP Installation, Sales or Engineering certifications, and your S200 or S202 license. Put them near the top, not in the footer.
- The two-meter setup. A simple photo or diagram of the production meter, net meter and disconnect answers a question before the customer asks it.
- A realistic timeline. Approval, agreement, permit, install, inspection and meter set. Say which steps you handle and which are up to the city.
- Your Utah license number, with a link to the state's free lookup.
- Reviews from Murray jobs. In BrightLocal's 2026 consumer survey, 47% of people said they won't use a business with fewer than 20 reviews.
Running your business in Murray
Murray says anyone conducting business within the city needs a valid business license. Its fee schedule lists a $100 base fee plus $6 per employee, full-time or part-time, and each location needs its own license. The city doesn't offer interim licenses. Home occupations need a license too, and the city's rules bar on-site carpentry, cabinet making and similar work that creates noise, dust or fumes in residential zones. Business licensing is at (801) 270-2425.
The Murray Area Chamber of Commerce, at 141 East 5600 South, has served Murray businesses since 1948.
What does a website cost?
At RedE Websites, a one-page Starter site is $500, a Template site is $1,500 and a Custom site is $2,500. Hosting starts at $100 a month and includes SSL security, maintenance and updates. Every site is mobile-friendly and SEO-ready, and you can edit it yourself anytime. We're based in Payson, about 50 minutes south. See our Murray web design page or compare plans.
Quick answers
Who provides electricity in Murray, Utah?
Murray City Power, a publicly owned municipal electric utility created in 1913.
Do solar installers need NABCEP certification in Murray?
Yes. Murray says a NABCEP Installation Certification has been mandatory for all solar installers in the city since April 2025.
How much is a net meter in Murray?
The city's checklist lists $250 for a residential net meter, paid to Murray City Power.
Can I turn on solar panels before Murray installs the net meter?
No. The city says panels may not be connected until the new net meter is installed.
Installing solar in Murray? Get a quote or call (801) 899-3580.
Sources
- Murray City: Power
- Murray City: Net metering and solar information
- Murray City: Solar checklist
- Murray City: Business licensing
- Murray City: License fee schedule
- Murray City: Home occupation licensing
- UDOT: Midvalley Express grand opening
- U.S. Census Bureau QuickFacts: Murray city, Utah
- Utah Population Committee subcounty estimates, May 2026
- Murray Area Chamber of Commerce
- BrightLocal Local Consumer Review Survey 2026
- Utah license lookup (DOPL)